Previous Jobs
- Tierra Construction
Owner: LBC Terminals
Contract Amount: $820,198.00
Sheet Pile Retaining Wall, LBC Terminals - A new steel sheet pile wall, complete with double channel wales, tie rods and sheet pile anchor wall was installed to allow expansion of the access road along the edge of the existing drainage ditch.

- Rosiek Construction
Owner: Corps of Engineers, Wallisville Locks & Dam
Contract Amount: $451,425.44
Corps of Engineers, Wallisville Locks & Dam - The project consisted of driving over 400 battered timber piling and 600 LF of vinyl sheet piling for the foundation and cut-off walls of the new gate structure. The new dam approach walls consisted of 12: thick precast concrete sheet piling supported by 18” battered concrete bearing piles.

- Primetex Corporation
Owner: MD Harbor
Contract Amount: $480,508.00
SH 2094 Water Control Structure - A steel sheet pile wall was driven across the old cooling water outfall channel. Upstream and downstream cofferdams were installed to install the decorative concrete to below the water level to complete the installation for the new residential complex.

- Inland Construction
Owner: USCG Galveston
Contract Amount: $363,050.00
USCG Galveston - After Hurricane Rita destroyed part of the existing concrete sheet pile breakwater, the broken concrete pile cap and broken sheet piling were removed from the slip. New concrete sheet pilings were driven and the new cast-in-place concrete caps were constructed to complete the repairs.

- Raw Water Intake Structure, Earthwork and Pump Station
Owner: Houston Area Water Corporation (City of Houston)
Contract Amount: $4,567,632.00
Raw Water Intake Structure for Northeast Purification Plant, Lake Houston. A 66’ diameter sheet pile cell was constructed in the lake to access the lake bottom in 23’ of water. A second braced rectangular sheet pile tunnel pit was installed to allow the 84” bore from 20’ deeper. The 84” intake pipe was installed from the offshore intake structure to the onshore pumping station, some 550’ away.

- Vince Bayou Railroad Bridge Replacement
Port Terminal Railroad Association
Contract Amount: $427,815.00
Railroad bridge for Port Terminal Railroad Association, Pasadena, Texas. The existing timber railroad bridge was removed and a new pile-supported pre-cast concrete bridge was constructed between an active track and active pipelines.

- Agrifos Plant – Pasadena, TX / New elevator structure complete with all equipment.
Owner: Agrifos Fertilizer
Contract Amount: $750.000.00
Plant remained in operation while support tower was replaced and existing building demolition on top of rock silos. During shut down, 150’ elevator was replaced and new rock mill was installed.

- Repair of Wharf and Fender System @ Wharves 23, 24 & 25
Owner: Port of Houston Authority
(Manatts, Inc.)
Contract Amount: $530,414.00
After demolition of the existing timber fender system, new 78’ long H-Piling are being driven and a new timber-faced steel frame fender system is being erected in sections and secured to the existing wharf. The 1800’ long project is being completed in 600’ phases.

- Sims Bayou Bulkhead
Owner: Phibro Refining, Inc.
Contract Amount: $430,000.00
The existing failed sheet pile bulkhead was removed and replaced with a new anchored sheet pile bulkhead, consisting of 75 ft. long H-Piling driven on a 1:1 batter, an H-Pile wale system, and 38 ft. long sheet piling. All of the work was performed from the water with a barge-mounted crane.

- Installation of Raw Water Intake Manifold – Lake Granbury
Owner: AES Wolf Hollow Plant
(TEPSCO)
Contract Amount: $678,000.00
Six piers were drilled into the lake bottom and three concrete pier caps were poured underwater to support the pre-fabricated intake manifold for the new power plant. Divers set the forms, placed the concrete and drilled in anchor bolts to secure the manifold, which was lowered by airbags in controlled descent.


